3 Common Mistakes to Avoid in Primavera P6 Scheduling (With How-To Guidance)

1. Neglecting the Work Breakdown Structure (WBS)

  • Mistake: Jumping directly into activity creation without building a comprehensive WBS.
  • Why It’s a Problem: A poorly defined WBS results in disorganized schedules, making management and reporting difficult.

Solution in Primavera P6:

1. Create a WBS:

  • Go to Project > WBS or use the WBS Window.
  • Click Add to create WBS elements for each major deliverable.
  • Use the Indent/Outdent buttons to define hierarchy levels.
Primavera P6

2. Assign Activities:

  • Open the Activities Window and assign activities to WBS elements using the WBS Column.
Assign Activities

3. Validate the Structure:

  • Use the Gantt Chart to view the WBS hierarchy and ensure all elements align with the project’s goals.

2. Improper Activity Sequencing

  • Mistake: Creating activities without clearly defining logical relationships.
  • Why It’s a Problem: Incorrect sequencing leads to an unreliable critical path and inaccurate timelines.

Solution in Primavera P6:

1. Define Relationships:

  • Open the Activities Window.
  • Go to the Predecessors/Successors tab in the Details Pane and add relationships.

2. Use the Right Relationship Types:

  • Choose the appropriate dependency: Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), or Start-to-Finish (SF).
Improper Activity Sequencing

3. Check Sequence Validity:

  • Use Schedule > F9 to run the schedule and check for logical gaps or errors.
  • Visualize relationships in the Activity Network View or the Trace Logic View.

3. Overlooking Calendar Settings

  • Mistake: Applying incorrect or default calendars to activities and resources.
  • Why It’s a Problem: Misaligned calendars lead to inaccurate durations and work schedules.

Solution in Primavera P6:

1. Define Calendars:

  • Go to Enterprise > Calendars and create project-specific, resource, or global calendars.
Overlooking Calendar Settings

2. Set Calendar Working Hours:

  • For each calendar, define working days, non-working days, and hours by selecting Modify.
Set Calendar Working Hours

3. Assign Calendars:

  • Assign calendars to activities in the Activities Window under the General Tab in the Details Pane.
  • Assign resource calendars in Enterprise > Resources by editing the Resource Details.
Assign Calendars

Recent Posts

Transitioning from Primavera P6 to Oracle Primavera Cloud: Resource Analysis

June 17, 2025

Transitioning from P6 to Oracle Primavera Cloud:Resource Analysis Resource Analysis: Primavera P6 vs. Primavera Cloud…

Read More

Training

June 16, 2025

Global Project Management Course Offerings Global PM offers comprehensive, hands-on training for project management professionals,…

Read More

Transitioning from Primavera P6 to Oracle Primavera Cloud: Mastering Resource Management

June 5, 2025

Transitioning from P6 to Oracle Primavera Cloud: Mastering Resource Management Switching from Primavera P6 to…

Read More

Agile Project Management in Construction? A Modern Approach to Building Smarter

June 3, 2025

In an industry known for tight deadlines, complex stakeholder relationships, and ever-changing site conditions, Agile…

Read More

Primavera P6 to Oracle Primavera Cloud: The EPS vs. Workspaces

May 20, 2025

Primavera P6 to Oracle Primavera Cloud: The EPS vs. Workspaces Author: Kari Jackson, PMP, PMI-ACP…

Read More