3 Common Mistakes to Avoid in Primavera P6 Scheduling (With How-To Guidance)

1. Neglecting the Work Breakdown Structure (WBS)

  • Mistake: Jumping directly into activity creation without building a comprehensive WBS.
  • Why It’s a Problem: A poorly defined WBS results in disorganized schedules, making management and reporting difficult.

Solution in Primavera P6:

1. Create a WBS:

  • Go to Project > WBS or use the WBS Window.
  • Click Add to create WBS elements for each major deliverable.
  • Use the Indent/Outdent buttons to define hierarchy levels.
Primavera P6

2. Assign Activities:

  • Open the Activities Window and assign activities to WBS elements using the WBS Column.
Assign Activities

3. Validate the Structure:

  • Use the Gantt Chart to view the WBS hierarchy and ensure all elements align with the project’s goals.

2. Improper Activity Sequencing

  • Mistake: Creating activities without clearly defining logical relationships.
  • Why It’s a Problem: Incorrect sequencing leads to an unreliable critical path and inaccurate timelines.

Solution in Primavera P6:

1. Define Relationships:

  • Open the Activities Window.
  • Go to the Predecessors/Successors tab in the Details Pane and add relationships.

2. Use the Right Relationship Types:

  • Choose the appropriate dependency: Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), or Start-to-Finish (SF).
Improper Activity Sequencing

3. Check Sequence Validity:

  • Use Schedule > F9 to run the schedule and check for logical gaps or errors.
  • Visualize relationships in the Activity Network View or the Trace Logic View.

3. Overlooking Calendar Settings

  • Mistake: Applying incorrect or default calendars to activities and resources.
  • Why It’s a Problem: Misaligned calendars lead to inaccurate durations and work schedules.

Solution in Primavera P6:

1. Define Calendars:

  • Go to Enterprise > Calendars and create project-specific, resource, or global calendars.
Overlooking Calendar Settings

2. Set Calendar Working Hours:

  • For each calendar, define working days, non-working days, and hours by selecting Modify.
Set Calendar Working Hours

3. Assign Calendars:

  • Assign calendars to activities in the Activities Window under the General Tab in the Details Pane.
  • Assign resource calendars in Enterprise > Resources by editing the Resource Details.
Assign Calendars

Recent Posts

3 Reasons Our CTO Recommends SQL Server for Your Primavera P6 Database

January 14, 2025

As Chief Technology Officer at Global PM, I focus on helping our clients optimize their…

Read More

Convert Your Primavera Cloud Schedule to Primavera P6 XER format

January 10, 2025

Mastering Schedule Conversion: From Primavera Cloud (XML) to Primavera P6 (XER) Introduction When working on…

Read More

Ask P6

January 9, 2025
Read More

Maximize Your P6 Investment with Training

January 3, 2025

Maximize Your Investment: 5 Reasons to Supplement Primavera P6 with Training Maximize Your Investment: 5…

Read More

Comprehensive Cost Comparison Between Primavera P6 and Oracle Primavera Cloud (OPC) for 5 Users with Global PM Discounts

January 2, 2025

Selecting the right project management solution often involves balancing features, costs, and value-added benefits. Both…

Read More