WHAT IS A LEVEL OF EFFORT ACTIVITY IN PRIMAVERA P6?

Level of Effort Activity Overview

The Level of Effort Activity in Primavera P6 is a type of special activity that has a duration that is not entered by a user. Rather, it is based on the dates calculated by the successors and predecessors (and their durations) in a particular path. Primavera P6 will calculate a summary / Level of Effort (LOE) activity.

Level of Effort Activity in Primavera P6

We all know that Level of Effort Activity has been designed for the representation of work on different projects. It is the type of work that does not contributed to the results of the project but it summarizes work progress. Some of the Level of Effort Activity in Primavera P6 examples are:

• Maintenance of equipment
• Safety Meetings
• Customer / contractor meetings

Problem: I don’t see my LOE activity bar in the Gantt Chart! 

The main reason this happens is that the Level of Effort bars do not display by default. To fix this, right click on your Gantt Chart, and choose Bars. Then ‘Display’ the following bars:

Question: Is the LOE critical? 

No, it is merely a summary of a network within your project schedule. It may summarize a critical path though!

Question: How do I tie my LOE in (with logic)?

The short answer is.. Most people link it in a Start to Start relationship with the first activity in that network and a Finish to Finish with the last activity.

Have questions?

Please contact us at Global PM at any time! We would love to help.

Recent Posts

Training

June 16, 2025

Global Project ManagementCourse Offerings Global PM offers comprehensive, hands-on training for project management professionals, specializing…

Read More

Resource Analysis: Comparing Primavera P6 and Oracle Primavera Cloud

June 16, 2025

Resource Analysis: Primavera P6 vs. Primavera Cloud If you’re a long-time Primavera P6 user navigating…

Read More

Transitioning from Primavera P6 to Oracle Primavera Cloud: Mastering Resource Management

June 5, 2025

Transitioning from P6 to Oracle Primavera Cloud: Mastering Resource Management Switching from Primavera P6 to…

Read More

Agile Project Management in Construction? A Modern Approach to Building Smarter

June 3, 2025

In an industry known for tight deadlines, complex stakeholder relationships, and ever-changing site conditions, Agile…

Read More

Primavera P6 to Oracle Primavera Cloud: The EPS vs. Workspaces

May 20, 2025

Primavera P6 to Oracle Primavera Cloud: The EPS vs. Workspaces Author: Kari Jackson, PMP, PMI-ACP…

Read More