Unlocking Project Success with Earned Value Management: A Dive into Pool Building
Are you managing a project and want to get a clear, quantifiable picture of its performance? Enter Earned Value (EV) Management—a powerful technique that brings clarity to project performance by comparing the amount of work planned versus what’s actually accomplished, and how much it costs. Let’s dive into the basics of Earned Value Management and explore its application with a practical example: building a swimming pool.
What is Earned Value Management?
Earned Value Management (EVM) is a project management technique that offers a snapshot of your project’s performance. It integrates three key aspects:
– Scope: What work was planned versus what has been completed.
– Schedule: How timely the work is compared to the schedule.
– Cost: How the actual expenditure compares to the budget.
Key Earned Value Measures:
– Budget at Completion (BAC): The total budget allocated for the entire project.
– Planned Value (PV): The budgeted cost of the work that was scheduled to be completed by a specific date.
– Earned Value (EV): The budgeted cost of the work that has actually been completed by a specific date.
– Actual Cost (AC): The real cost incurred for the work completed by a specific date.
Case Study: Building a Swimming Pool
Let’s use the example of constructing a swimming pool to illustrate how Earned Value Management works.
Project Details:
– Total Budget (BAC): $50,000
– Project Duration: 5 months
– Monthly Planned Value (PV): $10,000 (assuming the budget is evenly distributed)
Scenario at the End of Month 3:
– Planned Value (PV): $30,000 (3 months x $10,000)
– Activity % Complete: 65% (This means 65% of the total project work is done)
– Actual Cost (AC): $28,000 (Actual expenditure incurred so far)
Calculations:
1. Earned Value (EV):
\[ EV = \text{% Complete} \times \text{BAC} \]
\[ EV = 65\% \times \$50,000 = \$32,500 \]
2. Schedule Variance (SV):
\[ SV = EV – PV \]
\[ SV = \$32,500 – \$30,000 = \$2,500 \]
A positive SV indicates the project is ahead of schedule.
3. Cost Variance (CV):
\[ CV = EV – AC \]
\[ CV = \$32,500 – \$28,000 = \$4,500 \]
A positive CV shows the project is under budget.
4. Schedule Performance Index (SPI):
\[ SPI = \frac{EV}{PV} \]
\[ SPI = \frac{\$32,500}{\$30,000} = 1.08 \]
An SPI greater than 1 means the project is progressing faster than planned.
5. Cost Performance Index (CPI):
\[ CPI = \frac{EV}{AC} \]
\[ CPI = \frac{\$32,500}{\$28,000} = 1.16 \]
A CPI greater than 1 indicates the project is spending less than planned for the work completed.
—
Summary:
In our swimming pool project example, by the end of Month 3, the project is ahead of schedule and under budget. Earned Value Management provides a valuable early warning system, allowing project managers to identify and address variances proactively. With EVM, you can make informed decisions to keep your project on track, whether you need to accelerate work or adjust costs.
Ready to implement Earned Value Management in your projects? Understanding these metrics will help you stay on top of your project’s performance and steer it toward success!
Recent Posts
Is Primavera P6 the Right Project Management Tool for Your Team?
Is Primavera P6 the Right Project Management Tool for Your Team? There are countless project…
Read MorePRIMAVERA SOFTWARE Post
PRIMAVERA SOFTWARE Overview Oracle’s Primavera P6 Professional Project Management (PPM) is a Windows-based project scheduling…
Read MoreCan Procore Be Integrated with Primavera P6?
Can Procore Be Integrated with Primavera P6? In a word, YES! Integrating Oracle’s Primavera P6…
Read MorePrimavera P6 24.12: Game-Changing Features Every Scheduler Needs to Know
Primavera P6 24.12: Game-Changing Features Every Scheduler Needs to Know If you’re managing projects with…
Read MoreOracle Primavera Cloud: Game-Changing Features in Version 25.5
Oracle Primavera Cloud 25.5: Game-Changing Features You Need to Know Author: Trey Miller, PMP,…
Read More