Level of Effort Activity in Primavera P6

Level of Effort activity usually consists of short amounts of work that must be repeated periodically. A Level of Effort (LOE) activity has a duration which is determined by its dependent activities.

When to use Level of Effort Activity?

Level of Effort activities can be used for on-going tasks that depend on other activities. For example, you could assign level of effort activities for safety meetings (over the life of the project), clerical work, or even some aspects of project management. A project manager who manages one project or multiple projects may be assigned 1 hour/day to Level-of-Effort activities in each project to complete administrative tasks. Level of Effort is used to define the amount of work performance within a time and is measured in staff days or staff hours per day/week/month.

Note: LOE activities are not critical and therefore cannot “drive out” the finish of a project. Safety meetings don’t push the project’s finish date out, they merely span the life of the project.

Working with Level of Effort Activity in Primavera P6

The predecessors and successors are used to get dates and durations of level of effort activities performed. In order to automatically calculate these durations and dates, you need to assign FF relationship to successor and SS relationship to predecessor. After you add Level of Effort activity and create relationships, project must be rescheduled.

By default, Level of Effort activities in Gantt Chart are not visible. You must format Bars in a Gantt Chart in order to display level of effort activities.

Recent Posts

About the Louisiana Workforce Commission’s Incumbent Workforce Training Program (IWTP)

April 11, 2024

Introduction to IWTP The Louisiana Workforce Commission’s Incumbent Workforce Training Program (IWTP) is designed to…

Read More

Exciting News: Introducing PMI-ACP Exam Prep Training at Global PM!

April 2, 2024

We are thrilled to announce a new addition to our training portfolio here at Global…

Read More

Five Key Features of P6 Professional Release 23.12

March 5, 2024

This latest version introduces several valuable enhancements. Let’s delve into the key features of P6…

Read More

Demystifying the DCMA 14-Point Schedule Assessment

February 26, 2024

Image: This is a snippet from Primavera P6 EPPM’s Schedule Check report.   Introduction: In…

Read More

Global PM’s Top 5 Reasons to Pursue Project Scheduling as a Career!

February 1, 2024

Embarking on a career in project scheduling can be both fulfilling and impactful. Here are…

Read More