How to Display Rain Days in Primavera P6

Accounting for times when no work takes place in Primavera P6 can help you keep your projects on track. Take the recent influx of rain in the south as an example. Contractors need to show that no work took place those days because of something outside of their control. 

Without documenting non-interval workdays, projects might display as being further ahead than they really are. This can impact everything from budgets to deliverables and more. Your customers need the most accurate records so they can set the right expectations.

Here’s how to note non-work intervals in Primavera P6.

Activate the Gantt Chart Bars

On the Gantt charts in Primavera P6, non-workdays can be displayed as a thin “neck” in between larger bars showing the days worked. To activate this visual, go to the Layout tool and select Bars. Highlight the Non-Critical Work Bar, then set Timescale to Remain Bar. Follow these same steps for Actual Work and Critical Work.

Advance the Data Date to Illustrate Non-Work Intervals

Next, you can advance the data date to show the work’s true progress. Go to Schedule, then advance the project date however far ahead the non-interval workdays set you back. For instance, if you lost two regular workdays due to uncontrollable circumstances, you’d advance the data date by two days. 

Suspend and Resume Non-Interval Work

You can add the Suspend Activity and Resume Activity columns in your activities to show what activities are affected. Activate these columns by selecting Columns from the Layout menu. You can also enter suspend and resume dates in the Status section of the Status tab.

In the example below, work stopped on

Your Gantt chart will update accordingly to show the non-interval workdays. 
Need more help with Primavera P6? Please take a look at our learning options.

Recent Posts

Primavera P6 Professional Free Trial: Easy Install Guide for Beginners

April 22, 2025

Downloading and Installing Primavera P6 Professional Version 24.12 – Made Easy! Overview This guide walks…

Read More

Top 5 Reasons to Get Agile Certified with PMI-ACP

April 8, 2025

Top 5 Reasons to Get Your Agile Certification: PMI-ACP If you’re serious about advancing your…

Read More

The Progress Line in Primavera P6 Professional

April 3, 2025

What is that Red Progress Line in Primavera P6? By: Trey Miller, PMP, PMI-SP Primavera…

Read More

XER vs. XML Files in Primavera P6: Which One Should You Use?

March 10, 2025

XER vs. XML Files in Primavera P6: Which One Should You Use? When managing projects…

Read More

Microsoft Project Online vs. Oracle Primavera Cloud: Which is Best for You?

February 25, 2025

MS Project Online vs. Primavera Cloud: Which is Best? Choosing the right cloud-based project management…

Read More