How to Display Rain Days in Primavera P6

Accounting for times when no work takes place in Primavera P6 can help you keep your projects on track. Take the recent influx of rain in the south as an example. Contractors need to show that no work took place those days because of something outside of their control. 

Without documenting non-interval workdays, projects might display as being further ahead than they really are. This can impact everything from budgets to deliverables and more. Your customers need the most accurate records so they can set the right expectations.

Here’s how to note non-work intervals in Primavera P6.

Activate the Gantt Chart Bars

On the Gantt charts in Primavera P6, non-workdays can be displayed as a thin “neck” in between larger bars showing the days worked. To activate this visual, go to the Layout tool and select Bars. Highlight the Non-Critical Work Bar, then set Timescale to Remain Bar. Follow these same steps for Actual Work and Critical Work.

Advance the Data Date to Illustrate Non-Work Intervals

Next, you can advance the data date to show the work’s true progress. Go to Schedule, then advance the project date however far ahead the non-interval workdays set you back. For instance, if you lost two regular workdays due to uncontrollable circumstances, you’d advance the data date by two days. 

Suspend and Resume Non-Interval Work

You can add the Suspend Activity and Resume Activity columns in your activities to show what activities are affected. Activate these columns by selecting Columns from the Layout menu. You can also enter suspend and resume dates in the Status section of the Status tab.

In the example below, work stopped on

Your Gantt chart will update accordingly to show the non-interval workdays. 
Need more help with Primavera P6? Please take a look at our learning options.

Recent Posts

Transitioning from Primavera P6 to Oracle Primavera Cloud: Resource Analysis

June 17, 2025

Transitioning from P6 to Oracle Primavera Cloud:Resource Analysis Resource Analysis: Primavera P6 vs. Primavera Cloud…

Read More

Training

June 16, 2025

Global Project Management Course Offerings Global PM offers comprehensive, hands-on training for project management professionals,…

Read More

Transitioning from Primavera P6 to Oracle Primavera Cloud: Mastering Resource Management

June 5, 2025

Transitioning from P6 to Oracle Primavera Cloud: Mastering Resource Management Switching from Primavera P6 to…

Read More

Agile Project Management in Construction? A Modern Approach to Building Smarter

June 3, 2025

In an industry known for tight deadlines, complex stakeholder relationships, and ever-changing site conditions, Agile…

Read More

Primavera P6 to Oracle Primavera Cloud: The EPS vs. Workspaces

May 20, 2025

Primavera P6 to Oracle Primavera Cloud: The EPS vs. Workspaces Author: Kari Jackson, PMP, PMI-ACP…

Read More