How many activities can you have in a P6 EPPM schedule?

[price-item item_number=”6″ category=”PRICE_TABLE_CATEGORY”]So, there is a lot of question as to how many activities you can have in a P6 schedule, specifically within the web interface of P6. We can put this to rest now!

How many activities can you have in a schedule (within in the P6 web interface)?

5,000 vs. unlimited. That is the question!

There is no limit to the number of activities you can have in a project.  The web can be limited for performance reasons.  There is an admin application setting that controls the number of activities that can be displayed in the Activity View.

In the Maximum Activities per Activity View field, enter the maximum number of activities that can display in the Activities tab of the Projects section.

If greater than 5,000, the Maximum memory allocated to Java Applets setting must be 128 or greater. The default is 5,000. Enter anything from 1 – 100,000.

Recent Posts

About the Louisiana Workforce Commission’s Incumbent Workforce Training Program (IWTP)

April 11, 2024

Introduction to IWTP The Louisiana Workforce Commission’s Incumbent Workforce Training Program (IWTP) is designed to…

Read More

Exciting News: Introducing PMI-ACP Exam Prep Training at Global PM!

April 2, 2024

We are thrilled to announce a new addition to our training portfolio here at Global…

Read More

Five Key Features of P6 Professional Release 23.12

March 5, 2024

This latest version introduces several valuable enhancements. Let’s delve into the key features of P6…

Read More

Demystifying the DCMA 14-Point Schedule Assessment

February 26, 2024

Image: This is a snippet from Primavera P6 EPPM’s Schedule Check report.   Introduction: In…

Read More

Global PM’s Top 5 Reasons to Pursue Project Scheduling as a Career!

February 1, 2024

Embarking on a career in project scheduling can be both fulfilling and impactful. Here are…

Read More