WHAT IS A LEVEL OF EFFORT ACTIVITY IN PRIMAVERA P6?

Level of Effort Activity Overview

The Level of Effort Activity in Primavera P6 is a type of special activity that has a duration that is not entered by a user. Rather, it is based on the dates calculated by the successors and predecessors (and their durations) in a particular path. Primavera P6 will calculate a summary / Level of Effort (LOE) activity.

Level of Effort Activity in Primavera P6

We all know that Level of Effort Activity has been designed for the representation of work on different projects. It is the type of work that does not contributed to the results of the project but it summarizes work progress. Some of the Level of Effort Activity in Primavera P6 examples are:

• Maintenance of equipment
• Safety Meetings
• Customer / contractor meetings

Problem: I don’t see my LOE activity bar in the Gantt Chart! 

The main reason this happens is that the Level of Effort bars do not display by default. To fix this, right click on your Gantt Chart, and choose Bars. Then ‘Display’ the following bars:

Question: Is the LOE critical? 

No, it is merely a summary of a network within your project schedule. It may summarize a critical path though!

Question: How do I tie my LOE in (with logic)?

The short answer is.. Most people link it in a Start to Start relationship with the first activity in that network and a Finish to Finish with the last activity.

Have questions?

Please contact us at Global PM at any time! We would love to help.

Recent Posts

How to Use Activity Steps in Primavera P6: A “Step-by-Step” Guide

November 22, 2024

What are Activity Steps in P6? Activity steps allow you to break down activities into…

Read More

Exporting Data from Primavera P6 and Creating Histograms & S-Curves in Microsoft Excel

November 14, 2024

Managing complex projects often involves analyzing data visually to make informed decisions. One effective way…

Read More

Mastering Primavera P6: 3 Tips to Make Learning a Breeze a Little Easier

November 5, 2024

Primavera P6 is a powerful project management tool used by professionals worldwide to plan, manage,…

Read More

Mastering Project Success: A Step-by-Step Guide to Using Baselines in Primavera P6

October 18, 2024

What is a Baseline? In project management, a project baseline serves as a snapshot of…

Read More

PMP vs PMI-SP Certifications: Choosing the Right Path for Your Career

October 10, 2024

Choosing Between PMP and PMI-SP Certifications: What You Need to Know In the world of…

Read More