Improve Decision Making Using Multiple Float Paths in Primavera P6
Enter description text here. Lorem ipsum dolor sit amet, consectetur adipiscing. Quo incidunt ullamco.
Understanding Total Float in Primavera P6
According to the PMBOK® Guide, Float (also called Slack) is: The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Float is often shared across a chain of connected activities. When one activity uses that float, the remaining activities along the same path lose those days as well. This can turn a near-critical path into a critical path and put your project completion date at risk.
Primavera P6's Multiple Float Paths feature helps identify these shared paths, making it easier to spot near-critical work before it becomes a problem.
In this article, we'll walk through three steps to use Multiple Float Paths:
- Set up a Float Path layout.
- Enable the Multiple Float Paths calculation.
- Run the schedule and review the results.
First, What Exactly Is a Float Path?
A float path is a string of logically linked activities drawing on one pool of float.
- Float Path 1 is the most critical chain, the one with the least float (normally zero).
- Float Path 2, 3 and onward each hold a little more float than the one before.
- Any length works. A path might be a single task or several dozen.
Start in Project > Activities and look at the Total Float column. You'll see plenty of numbers, but nothing tells you which activities share them.
Step 1: Build a Float Path Layout
Create a layout that makes the results easy to read. You'll reuse it on every schedule, so it's worth five minutes.
Right-click any column heading in the Activities window and pick Columns.... In Available Options, expand Multiple Float Paths, then move Float Path and Float Path Order across to Selected Options. Put Float Path at the top of the list with Float Path Order right below it. Make sure Total Float is also selected (it lives in the Durations group), then click OK.
Next, give each path its own band. Right-click a column heading, choose Group and Sort by, and set the first Group By row to Float Path. Untick Show Group Totals for a tidier view, then click OK.
Save the view with View > Layout > Save Layout As... and give it a clear name, such as Float Path Review. The Float Path column stays empty until P6 calculates it in Step 2.
Step 2: Switch On Multiple Float Path Calculation
Float paths are off by default. You turn them on in the scheduling options:
- Open Tools > Schedule (or press F9) and click Options....
- Go to the Advanced tab and tick Calculate multiple float paths.
- Under Calculate multiple paths using, choose between Free Float and Total Float. Free Float is my usual starting point, because it splits chains exactly where the sharing ends.
- Use the ... button under Display multiple float paths ending with activity to pick your finish milestone. In NOLACC that's A2430 Substantial Completion - All TCO.
- Leave Specify the number of paths to calculate at 10, click Close, and answer Yes when P6 asks to save the scheduling settings.
Step 3: Schedule and Read the Paths
Back in the Schedule window, click Schedule. P6 recalculates the dates and, with your new options, tags each activity with a float path number.
Your Activities window now shows numbered bands. Float Path 1 should be your critical path, carrying the lowest Total Float. The bands that follow hold chains with more float, and a band with only one activity means that task shares its float with nobody.
In this schedule, Float Path 1 starts at A1170 Second Floor Slab & Collar Beam, climbs through the upper floors, then the windows, stucco, paint, pool and pergola, and ends at Substantial Completion. Later bands hold anywhere from a few weeks to several months of float, while a handful sit just above the critical path. Those deserve a close watch.
For a start-to-finish reading order inside each band, click Sort... in the Group and Sort dialog and sort by Float Path Order.
Practical Tips
- Recalculate after each update. Progress and logic changes reshuffle the paths.
- Mind the gap. If Float Path 2 is only a day behind Float Path 1, you effectively have two critical paths.
- Share the layout. Use the Available to option in Save Layout As so other planners can open it.
- Run both bases. Calculating once on each basis reveals how fragile your paths are.
Common Issues
- Empty Float Path column. The option is off, or the project hasn't been rescheduled since you switched it on.
- Fewer paths than expected. P6 stops at the number you set, and small networks may simply have few chains.
- Float looks different from your diagram. Calendars, constraints and your chosen float basis each shift the result.
- Activities without a path. Open ends and missing logic can drop work out of the calculation, so fix logic first.
Conclusion
In three steps you built a reusable float path layout, enabled the multiple float path calculation and scheduled the project to see which chains share float. Seeing float as a resource shared along a chain, rather than a single row's figure, is what lets planners protect the finish date instead of explaining why it moved.