Improve Decision Making Using Multiple Float Paths in Primavera P6

Enter description text here. Lorem ipsum dolor sit amet, consectetur adipiscing. Quo incidunt ullamco.

Understanding Total Float in Primavera P6

According to the PMBOK® Guide, Float (also called Slack) is: The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.

Float is often shared across a chain of connected activities. When one activity uses that float, the remaining activities along the same path lose those days as well. This can turn a near-critical path into a critical path and put your project completion date at risk.

Primavera P6's Multiple Float Paths feature helps identify these shared paths, making it easier to spot near-critical work before it becomes a problem.

In this article, we'll walk through three steps to use Multiple Float Paths:

  1. Set up a Float Path layout.
  2. Enable the Multiple Float Paths calculation.
  3. Run the schedule and review the results.

First, What Exactly Is a Float Path?

A float path is a string of logically linked activities drawing on one pool of float.

  • Float Path 1 is the most critical chain, the one with the least float (normally zero).
  • Float Path 2, 3 and onward each hold a little more float than the one before.
  • Any length works. A path might be a single task or several dozen.

Start in Project > Activities and look at the Total Float column. You'll see plenty of numbers, but nothing tells you which activities share them.

Primavera P6 activities window showing the Total Float column, illustrating how float appears as an individual row's figure before being grouped by path.

Figure 1: Before - Project > Activities: the Total Float column

Step 1: Build a Float Path Layout

Create a layout that makes the results easy to read. You'll reuse it on every schedule, so it's worth five minutes.

Right-click any column heading in the Activities window and pick Columns.... In Available Options, expand Multiple Float Paths, then move Float Path and Float Path Order across to Selected Options. Put Float Path at the top of the list with Float Path Order right below it. Make sure Total Float is also selected (it lives in the Durations group), then click OK.

Primavera P6 Columns dialog box showing how to add Float Path and Float Path Order to the top of the Selected Options list.

Figure 2: Columns: Float Path and Float Path Order

Next, give each path its own band. Right-click a column heading, choose Group and Sort by, and set the first Group By row to Float Path. Untick Show Group Totals for a tidier view, then click OK.

Group and Sort dialog in Primavera P6, configured to group activities by Float Path with group totals turned off for a tidier view.

Figure 3: Right-click a column heading > Group and Sort by: Group By Float Path

Save the view with View > Layout > Save Layout As... and give it a clear name, such as Float Path Review. The Float Path column stays empty until P6 calculates it in Step 2.

Save Layout As dialog box in Primavera P6, demonstrating how to save and name the reusable layout as Float Path Review.

Figure 4: View > Layout > Save Layout As...

Step 2: Switch On Multiple Float Path Calculation

Float paths are off by default. You turn them on in the scheduling options:

  • Open Tools > Schedule (or press F9) and click Options....
  • Go to the Advanced tab and tick Calculate multiple float paths.
  • Under Calculate multiple paths using, choose between Free Float and Total Float. Free Float is my usual starting point, because it splits chains exactly where the sharing ends.
  • Use the ... button under Display multiple float paths ending with activity to pick your finish milestone. In NOLACC that's A2430 Substantial Completion - All TCO.
  • Leave Specify the number of paths to calculate at 10, click Close, and answer Yes when P6 asks to save the scheduling settings.
Advanced scheduling options in Primavera P6, showing the settings to calculate multiple float paths using Free Float and ending on a specific completion activity.

Figure 5: Tools > Schedule > Options... > Advanced tab

Watch out for one trap: ending the calculation on a random activity. Unless you're studying a particular milestone, point it at the project's last milestone so nothing in the network is left out.

Step 3: Schedule and Read the Paths

Back in the Schedule window, click Schedule. P6 recalculates the dates and, with your new options, tags each activity with a float path number.

Primavera P6 Schedule dialog box highlighting the Schedule button to recalculate dates and the Options button to access advanced settings.

Figure 6: Before - Tools > Schedule

Your Activities window now shows numbered bands. Float Path 1 should be your critical path, carrying the lowest Total Float. The bands that follow hold chains with more float, and a band with only one activity means that task shares its float with nobody.

In this schedule, Float Path 1 starts at A1170 Second Floor Slab & Collar Beam, climbs through the upper floors, then the windows, stucco, paint, pool and pergola, and ends at Substantial Completion. Later bands hold anywhere from a few weeks to several months of float, while a handful sit just above the critical path. Those deserve a close watch.

For a start-to-finish reading order inside each band, click Sort... in the Group and Sort dialog and sort by Float Path Order.

Primavera P6 activities window displaying the calculated multiple float paths, with Float Path 1 highlighted as the critical path and sorted by Float Path Order to show the work sequence.

Figure 7: After - After scheduling: Float Path 1 is the critical path

Practical Tips

  • Recalculate after each update. Progress and logic changes reshuffle the paths.
  • Mind the gap. If Float Path 2 is only a day behind Float Path 1, you effectively have two critical paths.
  • Share the layout. Use the Available to option in Save Layout As so other planners can open it.
  • Run both bases. Calculating once on each basis reveals how fragile your paths are.

Common Issues

  • Empty Float Path column. The option is off, or the project hasn't been rescheduled since you switched it on.
  • Fewer paths than expected. P6 stops at the number you set, and small networks may simply have few chains.
  • Float looks different from your diagram. Calendars, constraints and your chosen float basis each shift the result.
  • Activities without a path. Open ends and missing logic can drop work out of the calculation, so fix logic first.

Conclusion

In three steps you built a reusable float path layout, enabled the multiple float path calculation and scheduled the project to see which chains share float. Seeing float as a resource shared along a chain, rather than a single row's figure, is what lets planners protect the finish date instead of explaining why it moved.

Want to go deeper into critical path analysis and schedule recovery? Explore Global PM's Primavera P6 software training, or visit globalpm.com to see how our team supports project controls professionals.