The Critical Path Explained: A Simple Guide Using a Backyard Shed

By Trey Miller, PMP, PMI-SP

The critical path is one of the most important ideas in project scheduling. Here's a plain-English explanation using a project we can all picture - building a backyard shed.

Two carpenters building a wooden backyard shed, used as a practical example to explain the Critical Path Method in project scheduling.

Figure 1: The critical path explained through a simple backyard shed build.

Introduction

If you've ever heard a scheduler talk about "the critical path" and nodded along without quite understanding what it meant, you're in good company. The term gets thrown around a lot, and most explanations dive straight into network diagrams and formulas without explaining why any of it matters.

The critical path is actually a simple idea. It's the sequence of activities that determines how long a project will take. Delay anything on it and the whole project slides. Delay something off it and you probably have some breathing room. The best way to see this in action is with a project everyone can picture - building a backyard shed.

The Project: Building a Backyard Shed

Here's the list of activities involved in building the shed. Each row shows the duration, what has to happen before it can start (the predecessor), the relationship type, and any lag between activities.

ID Activity Duration Predecessor Relationship Lag
A Prepare site 2 days — — —
B Order materials 3 days — — —
C Foundation 4 days A, B FS, FS 0, 0
D Frame walls + floor 4 days C FS 1 day
E Roof + exterior finish 6 days D FS 0
F Paint exterior 2 days E SS 3 days
G Doors + windows 2 days E FS 0
H Interior fit-out 3 days D SS 2 days
I Landscaping 4 days D SS 2 days
J Inspection + cleanup 1 day F, G, H, I FS 0
Figure 2: Activity list for the shed build. Rows shaded red are on the critical path.

A Quick Note on Relationships and Lags

You'll see two relationship types in the table above:

  • FS (Finish-to-Start): the successor can't start until the predecessor finishes. This is the most common relationship - you can't frame walls until the foundation is poured.
  • SS (Start-to-Start): the successor can start once the predecessor has started (usually with a lag). This is how you model activities that run in parallel - landscaping doesn't need framing to be complete, but it makes sense to wait until framing is a couple of days underway before the landscapers show up.

A lag is a delay added to a relationship. The concrete foundation needs a day to cure before you can frame on top of it — that's an $\text{FS}+1$ relationship. The paint crew can start once the exterior finish work is 3 days along — that's an $\text{SS}+3$ relationship.

Step 1: Draw the Network Diagram

The first move is to sketch the project as a network diagram. Each activity gets its own box, and arrows show which activities depend on which. Labels on the arrows show the relationship type and any lag.

A baseline CPM network diagram mapping out activity sequences and logic dependencies for a backyard shed build before schedule calculations.

Figure 3: The shed project as a network diagram. Notice how activities like Paint (F), Interior (H), and Landscaping (I) branch off in parallel - they don't all have to happen in sequence.

Step 2: Calculate the Earliest Start Times (Forward Pass)

Now work forward through the diagram. For each activity, calculate two numbers: the Earliest Start (ES) — the earliest day the activity can begin — and the Earliest Finish (EF) — the earliest day it can end. EF is just ES plus the activity's duration.

At merge points (nodes where multiple arrows come in), take the longest path. That's the key rule.

Walk through it: A (2 days) and B (3 days) both start on day 0. The foundation (C) can't start until both are done, so C starts on day 3 (B is the longer of the two). C finishes on day 7, but there's a 1-day cure lag before framing, so D starts on day 8 and finishes on day 12. E starts on day 12 and finishes on day 18. Paint (F) has an $\text{SS}+3$ relationship with E, so F can start on day 15. Doors and windows (G) start after E finishes, on day 18. Interior (H) and landscaping (I) both have $\text{SS}+2$ relationships with D, so they can start on day 10 while framing is still underway.

Everything eventually feeds into J (inspection), which can't start until the latest predecessor finishes - that's G on day 20. J takes 1 day, so the shed is done on day 21.

A project network diagram showing a forward pass schedule calculation to determine the earliest start and earliest finish times for each construction activity.

Figure 4: The network diagram with the forward pass complete. Each node shows ES (top-left) and EF (top-right). Total project duration: 21 days.

QUICK CHECK: At every merge point, always take the longest path in. If one predecessor gives you day 5 and another gives you day 8, the activity starts on day 8. The shorter path is where you'll find float.

Step 3: Calculate the Latest Finish Times (Backward Pass)

Now work backward from the end. The project has to finish on day 21, so the latest J can finish (LF) is day 21. Since J takes 1 day, its latest start (LS) is day 20 - meaning every predecessor of J has to be complete by day 20.

Work back through each activity, subtracting durations and accounting for lags. For most activities on the main chain (B, C, D, E, G, J), the LS matches the ES exactly - meaning those activities have zero slack. That's the critical path.

For the parallel branches, things get more interesting. Paint (F) has an ES of 15 but an LS of 18 — it has 3 days of float. Interior (H) has an ES of 10 but an LS of 17 — 7 days of float. Landscaping (I) has 6 days of float. Site prep (A) even has 1 day of float because materials delivery (B) takes a day longer.

What Is Float?

Float — sometimes called slack — is the amount of time an activity can be delayed without pushing the project end date. It's calculated as:

$$\text{Float} = \text{LS} - \text{ES} = \text{LF} - \text{EF}$$

An activity with zero float is on the critical path. Any delay to it delays the whole project by the same amount. An activity with float has slack — you can be late by up to that many days before it becomes a problem.

For the shed, this means the landscapers can be up to 6 days late without affecting the finish date. The interior crew has 7 days of buffer. The paint crew has 3 days. But the framing crew? Zero. Any delay to framing pushes the shed completion back day-for-day.

Step 4: Identify the Critical Path

Any activity with zero float is on the critical path. For the shed, that gives us the following chain:

B → C → D → E → G → J (21 days)

This is the sequence that determines the project duration. Everything else has some breathing room.

A completed CPM analysis network diagram highlighting the zero-float critical path in red, with calculated early/late dates and total float values displayed for each node.

Figure 5: The complete critical path analysis. Red boxes = critical path (float = 0). Green boxes = non-critical activities with float shown in each node.

Why the Critical Path Matters

The critical path tells you where to focus. If your framing crew is running behind, that's a critical-path problem - every day of delay pushes the finish back a day. If the landscapers are behind by 3 days, you're still fine. They have 6 days of float. That's the whole point.

On a small project like a shed, this might feel like overkill. On a large construction project with hundreds of activities and dozens of trades, the critical path is what keeps the whole thing moving. Software like Primavera P6 calculates it automatically, but understanding what it's doing under the hood is what separates a scheduler who can solve problems from one who just clicks buttons.

In Conclusion

The critical path is the backbone of every project schedule - the longest chain of dependent activities that determines the project duration. However, near-critical activities with limited float also require close attention because small delays can quickly impact the finish date. Monitoring both helps identify risks early and keeps projects on schedule.

Need Primavera P6 Training, Consulting Help, or Software?

Understanding the Critical Path Method is essential for delivering projects on time. Global PM provides the tools, training, and expertise to help organizations improve project planning, scheduling, and execution. For more than 25 years, we've helped thousands of professionals master project management through practical, real-world training and consulting.

Contact us today to learn how we can help your team succeed.

Training & Software Director: Wendy Jackson

Phone: (985) 781-9190

Email: wjackson@globalpm.com

Website: www.globalpm.com

Send Us a Message

  • This field is for validation purposes and should be left unchanged.